August 22, 2009: Groundbreaking August 27, 2009: Staff Groundbreaking September 16-October 13, 2009: Grading January-early February 2010: Pouring Concrete February 23 – March 12, 2010: Structural Steel March 12 – March 25, 2010: Shear and Bearing Walls May 5th: HVAC and Exterior walls May-June Construction Updates July Construction-The Veranda August-September Updates